Re-installation of Klargester BA BioDisc
After a period of bad weather, during which the level of ground water rose significantly, this tank was emptied and popped straight out of the ground. It had been incorrectly installed as it had no concrete to hold it in place.
The emptying company recommended the property owner call ESTS and, following an inspection, we were appointed to excavate and re-concrete the treatment plant back into position.
Once access had been made possible, this was exactly what we did, before wiring up and re-commissioning this Klargester BA BioDisc.